Every campsite owner knows the feeling. It has rained for three days, the grass pitches are churned up, and a motorhome is booked in for Friday. Hardstanding pitches are the fix most owners eventually reach for. They let you take bookings in wet weather, open for longer, and charge a little more for the privilege. They also cost real money and, done badly, turn into puddles of their own.
This guide walks through the main types of campsite hardstanding, roughly what they cost, how to build a pitch that drains properly, the planning questions to ask first, and how to price and sell those pitches once they are in. November and December are the ideal months to think about it. The ground is quiet, contractors are easier to book, and the work can settle before spring.
Why hardstanding pitches are worth it
Grass is lovely in July. In March, October and any wet week in between, it is a liability. Heavy vans sink, wheels spin, and you end up towing guests out with the tractor. Hardstanding solves that, and it brings a few other benefits with it:
- A longer season. If you want to open earlier, close later or stay open all year, you need pitches that work in winter. Our guide to opening all year covers the wider picture.
- Fewer cancellations and moves. You stop shuffling guests around because their booked pitch is under water.
- Motorhome demand. Many motorhome owners search specifically for hardstanding and will book elsewhere if you do not offer it.
- Less wear on the grass. Your remaining grass pitches get a rest, which keeps them looking better in summer.
- A higher nightly rate. Guests expect to pay a bit more for a firm, level pitch.
You do not need to convert the whole field. Most small sites start with two or three hardstanding pitches near the entrance and add more once they see how they book.
Types of campsite hardstanding
There are four common options. Each has a different cost, look and lifespan.
Gravel hardstanding
The most popular choice by a distance. A gravel pitch is dug out, lined with a geotextile membrane, filled with a compacted sub-base such as MOT Type 1, then topped with a layer of clean stone. It drains well, it is easy to repair, and you can do much of the work yourself if you have a digger and a roller. The downsides are that loose stone migrates onto the grass over time and needs topping up every few years.
Grass reinforcement grids
Plastic honeycomb grids are laid on a prepared base and either filled with gravel or with soil and grass seed. The grassed version keeps the field looking green while spreading the load of a heavy van. It is a good fit for CL and CS sites, or anywhere you want the field to look like a field. Grassed grids can still get soft in very wet spells, so they are not quite as reliable as full gravel.
Concrete or tarmac
Solid, clean and very hard wearing. Also the most expensive, the most permanent and the least forgiving if you get the levels wrong. Water runs off rather than soaking in, so you need to think about where it goes. Most small and medium sites reserve concrete or tarmac for roadways, service points and perhaps a few premium serviced pitches.
Half hardstanding
A popular compromise is a hard strip for the caravan or motorhome with grass alongside for the awning. Guests get a firm surface for the wheels and a soft one for pegs, and you spend less on materials. Make the hard area generous enough for the longer motorhomes you are now seeing, and leave room for a car.
How much does campsite hardstanding cost?
Costs vary hugely, so treat any figure as a starting point rather than a quote. The big variables are:
- Pitch size. A large motorhome pitch can need twice the stone of a compact caravan pitch.
- Dig depth. Soft clay needs a deeper sub-base than free-draining ground.
- Materials and haulage. Stone is heavy, and delivery to a rural site is often a big part of the bill.
- Labour. Doing it yourself with your own machinery is far cheaper than paying a groundworks contractor.
- Extras. Drainage, electric hook-up ducting and water points add to the total.
As a very rough guide, a DIY gravel pitch built with your own kit can come in at a few hundred pounds in materials. A contractor-built pitch with a full dig out, membrane, sub-base and top layer can easily pass a thousand pounds once labour and haulage are included. Grids and concrete usually cost more again. Get at least three written quotes, and ask each contractor to price the same specification so you are comparing like with like.
Then do the sums the other way. If a hardstanding pitch lets you take an extra 30 or 40 nights a year in spring and autumn, plus a small premium in summer, it often pays for itself within a couple of seasons.
Building a hardstanding pitch that drains
The single biggest mistake is laying stone straight onto soil. Within a season the stone sinks into the mud and you are back where you started. A sound pitch usually looks like this:
- Dig out the topsoil down to firm ground. Keep it, it is useful elsewhere.
- Lay a geotextile membrane to stop the sub-base mixing with the soil underneath.
- Add a compacted sub-base in layers, rolling each one.
- Finish with a top layer of clean, angular stone that locks together rather than rolling underfoot.
- Edge it with timber or kerbs so the stone stays where you put it.
Levels matter just as much. Motorhome owners hate a sloping pitch, but a perfectly flat one with nowhere for water to go will hold puddles. Aim for nearly level with a gentle fall away from where the door and awning will be. Think about where that water ends up too. If you are already fighting soggy ground, our guide to waterlogged pitches has more on drainage.
Finally, plan the services while the ground is open. Running ducting for electric hook-ups and water now is far cheaper than digging up a finished pitch later. If you are adding hook-ups, our electric hook-up guide covers the safety side.
Planning permission and club rules
This is the part people skip, and it can be expensive. Laying hardstanding is a physical change to the land, and depending on your site and your local authority it may need planning permission. Do not assume your existing campsite permission or exemption certificate covers it.
- Licensed sites should check their planning permission and site licence conditions. Some permissions restrict hard surfacing or the number and position of pitches.
- CL and CS sites operate under exemption certificates issued through the clubs. Speak to your club contact before laying anything permanent. They will know what is acceptable for your site, and some prefer grass or reinforced grass to keep the informal feel.
- Protected areas such as National Parks, AONBs (now called National Landscapes) and land near listed buildings often attract closer scrutiny.
A short email to your local planning team describing what you want to do will usually get you an answer. Keep a copy of the reply with your site records.
Pricing and selling your hardstanding pitches
Once your new pitches are in, make sure guests can see them and book them. A hardstanding pitch that sits in the diary looking exactly like a grass one is money left on the table.
- Charge a premium. A few pounds a night extra is normal and rarely questioned. Our pitch pricing guide explains how to set different rates by pitch type and season.
- Describe them clearly. Say how big they are, what the surface is, and whether they have electric. Motorhome owners want to know the length they can fit.
- Let guests choose. When guests book online, they should be able to pick hardstanding rather than hoping for it.
- Prioritise them in winter. Close your grass pitches for the wet months and keep the hardstanding open.
This is where good booking software earns its keep. In CampSuite you can set each pitch up with its own type, size and facilities on the parks and pitches page, price hardstanding differently from grass, and switch grass pitches off for winter with a click. Guests then see exactly what is available when they book online, and you stop getting phone calls asking which pitches are firm.
Keeping hardstanding in good shape
Hardstanding is low maintenance, not no maintenance. Add these jobs to your yearly routine:
- Rake stone back into place after busy weekends
- Top up thin areas each spring before the season starts
- Spray or pull weeds before they establish
- Check edges and kerbs for damage from wheels
- Look for new puddles after heavy rain, as they show where the base has sunk
Spotting a problem early means a barrow of stone rather than a full rebuild.
The short version
Hardstanding pitches let you take bookings in weather that would close a grass field, and they pay for themselves faster than most owners expect. Start small with a few gravel pitches, build them on a proper sub-base with a membrane, check planning and club rules before you dig, and run the services in while the ground is open. Then price them as the premium pitches they are and make them easy to book.
If you want guests to choose their pitch type when they book, and you want to stop juggling a paper diary every time the weather turns, you can set up CampSuite for free in about 15 minutes. It is free for CL and CS sites, and our pricing page shows what each plan includes for larger parks.